Countries

Global flag icon
Global
Albania flag icon
Albania
Brazil flag icon
Brazil
Chile flag icon
Chile
Croatia flag icon
Croatia
Finland flag icon
Finland
France flag icon
France
Germany flag icon
Germany
India flag icon
India
Ireland flag icon
Ireland
Italy flag icon
Italy
Netherlands flag icon
Netherlands
Norway flag icon
Norway
Peru flag icon
Peru
Poland flag icon
Poland
Portugal flag icon
Portugal
Spain flag icon
Spain
Sweden flag icon
Sweden
Türkiye flag icon
Türkiye
United Kingdom flag icon
United Kingdom
United States flag icon
United States
  • 2020
    Entered into operation
  • 197 MW
    Installed capacity
  • 450 GWh
    Annual production

Construction of Moglicë HPP started in 2015, and commercial operations were started in 2020.

Moglicë was the second hydropower plant to be completed by Devoll Hydropower Sh.A. (DHP), an Albanian-registered company, owned and operated by Statkraft.

Devoll Hydropower builds, owns and operates hydropower plants in cascade along the Devoll River in southeast Albania, based on a concession agreement signed between Statkraft and the Government of Albania.

The dam at Moglice hydropower plant
Moglicë dam and reservoir (Photo: Artan Figu )

Moglicë hydropower plant utilizes a head of 300 metres between 650 and 350 metres above sea level. The approximately 167 metres high dam is an asphalt-core rock-filled structure and is one the highest of its kind in the world. The reservoir has a storage capacity of approximately 380 million cubic metres and a surface area of approximately 7.2 square kilometres.

The plant receives water through a 10.7 kilometres long tunnel from the Moglicë reservoir and is equipped with two Francis turbine units and a small unit at the toe of the dam. The installed capacity is 197 MW with an average annual production of 450 GWh.

Moglice hydropower plant
The dam at Moglicë hydropower plant (Photo: Eduard Pagrja)

Moglicë hydropower plant is part of the Devoll Hydropower Project which consists of development, planning, construction and operation of both Banja and Moglicë, with a total installed capacity of approximately 269 MW and a planned annual production of approximately 700 GWh.

The concession agreement also includes an option for a third hydropower plant, Kokel.

Company Ownership share
Statkraft 100%

Find out more about our activities in Albania